A Massachusetts judge on Friday temporarily blocked a turbine manufacturer from pulling out of a major offshore wind farm project, saying it would be “fanciful” to imagine a new contractor could finish the installation. Vineyard Wind went to court last week after GE Renewables said it would be terminating its contracts for turbine services and maintenance. GE Vernova, the parent company for GE Renewables, argued that Vineyard Wind owes it $300 million for work it performed, but Vineyard Wind